Abilene School District Construction
"....our most precious national resource; our children, our future citizens”,
- Dwight D. Eisenhower.
Bond Issue passed!
1210 - Yes
570 - No
Web Site Updated: 5-29-15
Renderings.pdfBidding Information
Private Web Sites: (semi-private web sites available for subcontractors and suppliers)
McKinley | Kennedy |
| |
Timelinefor the Abilene School District's Facilities Study including steps thathave been taken and potential future steps. Supporting documents areprovided including Board of Education meeting minutes.
►Step 1: Board Receives 6-4-12 Facility Study from Dr. Kent Steward (Facility Study) (Dr. Stewart Response)
►Step 2: [8-22-12] BOE approves motion to Begin Master Plan Facilities Study with HTK Architects (BOE Minutes)
►Step 3: [12-10-12] Report from TRANE on Mechanical, Electrical and Plumbing (BOE Minutes) (/UserFiles/Servers/Server_321530/File/Trane.pdf)
►Step 3: Board Reviews Needs from Master Plan Process
Meeting 1 with Architect: [12-19-12] (BOE Minutes)
Meeting 2 with Architect: [1-21-13] (BOE Minutes)
Meeting 3 with Architect: [2-4-13] (BOE Minutes)
Meeting 4 with Architect: [2-27-13] (BOE Minutes)
Meeting 5 with Architect: [5-8-13] (BOE Minutes)
(Conceptual Drawings 1) (Conceptual Drawings 2) (Conceputal Drawings 3)
►Step 4: Citizen's Advisory Group (CAG)
Meeting 1: [6-28-13] Review of Needs from Master Plan including Conceptual Drawings and Stewart Study (CAG Meeting Minutes) (Surrounding Community Mill Levy rates)
Meeting 2: [July - August, 2013] Tours of the all schools including football stadium accompanied by Maintenance Director
Meeting 3: [8-21-13] Information from Staff, Administration, Dr. Stewart, and Bond Consultants (Dr. Stewart Response) (Staff Survey)
Meeting 4: [9-11-13] Discussion to begin identifying needs (CAG Meeting Minutes) (Bond and Interest State Aid Table)
Meeting 5: [10-2-13] Finalize plan to present to the BOE (CAG Meeting Minutes)
►Step 5: [10-11-13] Recommendation Presented to the BOE by Citizen's Advisory Group (Powerpoint) (Priorities)
►Step 6: [10-16-13] Board of Education Discussion in response to Citizens's Advisory Group Presentation (BOE minutes)
►Step 7: [10-22-13] Approachthe City about their interest in supporting a Sales Tax Option on aballot - City Disapproved resolution to research this proposal.
►Step 8: BOE to Complete Master Plan (November 4, 2013) (AHS) (AHS Possible Future) (AMS) (New 4-5) (McKinley) (Kennedy) (AHS-AMS-GradeSchool Possible Future)
10-30-13 BOE Meeting: Minutes
►Step 9: BOE to Discuss Resolution for a potential bond election (November - December, 2013)
11-11-13 BOE Meeting: Minutes
11-25-13 BOE Meeting: Minutes
12-9-13 BOE Meeting: Minutes
►Step 10: 12-11-13 BOE Approves a Resolution for facilities upgrade engaging in a bond election.
►Step 11: Provide material tothe community about the proposal, offering forums, and otherinformational venues (December, 2013 - March, 2014)
►Step 12: Election (APRIL 1ST, 2014)
►Step 13: BOND passes Programming with Staff begins
►Step 14: Architectural Plans finalized and Bidding Process begins (June - December 2014)
►Step 15: Begin building (January 2015)
►Step 16: Completion of all Project August 2016